Our company has extensive experience in diagnostics of the nuclear power plant equipment.
In 2020, thermal tests of TVV-500-2UZ turbine generators of TG-1, 2, 3, 5, 6, 7, 8 of the Kursk NPP were performed.
In addition, at the Kalinin NPP, the technical condition of the stator dismantled from the TG-1 was assessed.
In 2019, thermal tests of TVV-500-2MUZ turbine generator of TG-4 of the Kursk NPP were performed.
In 2019-2020, an operational assessment of the thermal state of the TVV-1000-4U3 turbine generator of Power Unit 4 was performed at the Balakovo NPP.
In 2018, the condition of the dismantled stator of the TVV-1000-4U3 turbine generator was examined at the Balakovo NPP to determine whether it can be further used as a reserve for unscheduled replacements.
In 2015-2017, at the Smolensk NPP, we performed:
In 2015, the tightness of the sealed enclosure of Units 1-4 of the Kola NPP was tested.
In 2014, the condition of mothballed TG-9,10 of Unit 5 at the Kursk NPP was surveyed.
In 2013, at the Kursk NPP, we: